Project profile
Aratinga Thermal Power Plant (Biomass)
O&M
Iqony Solutions do Brasil was hired by ERB to perform the following services: support in plant acceptance, support in commissioning, training, O&M support.
The plant consists of a cogeneration project of 150 tons/hour of steam and 17 MWe of generation. The plant includes a biomass processing unit, fluidized bed boiler with ESP. The plant is installed within the DOW chemical complex providing it with necessary utilities: energy and process steam.
Installed capacity | 17 MWe + 150 tons/h |
Commissioning | January 2014 - July 2014 (COD) |
Customer | ERB - Energia Renováveis do Brasil |
Execution of SES services | 2013 - 2015 |